Selwyn Community

Posted 15 Feb

Selwyn Community

Avanda Group is proud to be the principal sponsor of Selwyn Sounds for its 5th anniversary on 10 April 2021. Always a very popular event in Lincoln,  this year’s line-up will be a completely Kiwi one with no international acts, but the crowd is still expected to be at capacity of close to 12,000. Selwyn remains one of the fastest growing districts in all of New Zealand with towns such as Rolleston, Lincoln, Prebbleton and Leeston expanding rapidly over the last decade. Avanda has a master planned development in Rolleston and is working on launching several new projects to support the region and to continue growing new communities. We are happy to contribute to the community’s enjoyment with our support of Selwyn Sounds.

 

Related News


Crown Lynn Yards Update

Crown Lynn Yards, the second stage of our New Lynn project, had some great progress in March.

Resource consent and  the EPA have been granted (this is a big deal for us) and building consent lodgements have commenced. 

Civil and underground works have started – construction of underground services are underway and the first platforms for terraces almost complete. It is important that we get these works finished before the winter rain sets in.

It won’t be too long before construction is really visible on the site.

Exciting Growth in Rolleston

Exciting Growth in Rolleston

The Selwyn district continues to go from strength to strength with the recent announcement that an $85 million shopping centre will be built in Rolleston, with new eateries, cinema and a farmers market all set to further boost the rapidly growing town on Christchurch's doorstep. The district council expects 24,000 people to be in Rolleston – the district’s biggest town – by the year 2040. We are pleased to be contributing to that growth.

West Edge Stage 1 Update

West Edge Stage 1 Update

The final 2 blocks in stage 1, C and D, are almost complete, despite the challenges of lockdown.  We are looking forward to seeing these residents settled into their new homes.

Depending on the block, there are some minor internal works to complete before landscaping and commercial cleaning can be finished.
 
For health and safety reasons, final inspections will be scheduled by invitation with settlement expected in the second quarter of 2021.